Big fines for construction firms following fatality
18 February 2019
OLIVER CONNELL and Son Ltd and Rydon Construction Ltd have been fined after a worker fell to his death when a temporary platform collapsed.
Southwark Crown Court heard how, on 24 July 2015, Mr Vasile Nichitut was working on the fifth floor of the construction site at the Green Man Lane Estate, when he walked onto a temporary platform covering a vertical shaft, which collapsed beneath him. He fell approximately 14m and died as a result of his injuries.
An investigation by the Health and Safety Executive (HSE) found that Oliver Connell and Son Ltd had failed to ensure that work at height was properly planned, appropriately supervised and carried out in a safe and practicable manner. Specifically, there was no temporary works design for the platform and the company’s system for installing and inspecting it was inadequate.
Rydon Construction Ltd failed to plan, manage and monitor the work involving the temporary platform to ensure that, construction work is carried out without risks to health or safety. They failed to identify the lack of design drawings and carry out suitable checks on the platform.
Oliver Connell and Son Ltd, of Zanrose House, Horsenden Lane South, Greenford, pleaded guilty to breaching Regulation 4(1) of the Work at Height Regulations 2005, and have been fined £360,000 and ordered to pay costs of £4834.08.
Rydon Construction Ltd, of Rydon House, Station Road, Forest Row, pleaded guilty to breaching Regulation 13(1) of the Construction (Design and Management) Regulations 2015, and have been fined £500,000 and ordered to pay costs of £40,740.88.
After the hearing, HSE inspector Owen Rowley said: “The consequences of temporary works failing can be dire. All contractors involved must ensure that an effective system for managing the temporary works on site is established and adhered to. Crucially, all temporary works require a design to ensure that they are suitable for purpose.
“In this case the failure to manage the risks associated with temporary works and work at height led to the entirely preventable death of Mr Nichitut.”
- Worker crushed while fault finding
- Tips to protect peoples hearing at work
- Graham Mackrell sentenced for Hillsborough role
- Workplace noise hindering manufacturing workers
- Health and Safety Matters Podcast - Episode 39
- ‘Proportionate' approach to appliance testing advocated by IET
- Practitioner viewpoint - May 22
- Sole trader fined after worker injured
- 3M Heavy Manufacturing and Transportation Workshops
- Farm worker fatally injured by telehandler