£1.1M fine following offshore gas blast
31 May 2019
MARATHON OIL UK LLC (Marathon) has been fined £1,160,000 following an HSE investigation into a high-pressure gas release on its Brae Alpha offshore platform on Boxing Day 2015.

Aberdeen Sherriff Court heard that on 26 December 2015, an eight-inch diameter high pressure pipework in Module 14 of the platform suffered a catastrophic rupture as a result of ‘Corrosion Under Insulation’ (CUI), allowing over two tonnes of high-pressure methane gas to be released almost instantaneously.
The force of the high pressure blast caused significant and widespread damage within Module 14. The incident occurred whilst most of the 100 personnel on the platform were gathered in the accommodation block, in readiness for their Boxing Day meal, and away from the source of the blast.
An investigation by HSE found that Marathon Oil had failed to undertake any suitable and sufficient inspection of the pipework that would have allowed the company to identify the risk and prevent the hazard from materialising.
These failures resulted in personnel onboard the Brae Alpha platform being exposed to an unacceptable risk of serious personal injury or death from fire and explosion, and also led to HSE serving an Improvement Notice on Marathon Oil in January 2016, requiring the company to implement an effective hydrocarbon pipework inspection and maintenance regime.
Marathon pleaded guilty to breaching Regulation 4 (1) of the Offshore Installations (Prevention of Fire and Explosion, and Emergency Response) Regulations 1995 and Section 33(1) of the Health and Safety at Work Act 1974, at Aberdeen Sheriff Court. The company has been fined £1,160,000.
HSE inspector, Ahmedur Rezwan, said, “This incident is a further reminder of the ever-present hazards in oil and gas production, that if not rigorously managed can easily result in a potentially life-threatening event.”
“Corrosion Under Insulation (CUI) is a well-known risk and this incident should not have occurred. During any normal period of operations personnel could easily have been working in, or transiting through Module 14, and they would almost certainly have been killed or suffered serious injury. The timing of the incident and fact that the gas did not ignite was fortuitous.”
- Stress is the main reason for absence, shows research from GRiD
- Funding to help keep Scottish fishers safe
- Getting interactive with the ASFP
- WSH says workplace injuries declined in 2017
- Global partnership between Draeger and Shell renewed
- Third Corporate Manslaughter Conviction
- Fall leaves grandad with life-changing brain injuries
- Director prosecuted after employee falls six metres
- Company fined after failing to identify asbestos
- Worker fell to his death through fragile asbestos roof