Unsafe asbestos removal leads to fine
05 June 2019
A CONSTRUCTION company and its director have been fined after failing to ensure the safe removal of asbestos during demolition work.
Greater Manchester Magistrates’ Court heard how Sherwood Homes Limited was the client responsible for the demolition of Crowton Mill in Northwich. Peter Kiely was a director of the company when the results of an asbestos survey conducted in January 2017 were received that identified the presence of asbestos containing materials on the site. The extra work required to remove the asbestos increased the estimated costs and timescale for the completion of the demolition.
An investigation carried out by the Health and Safety Executive (HSE) found that Sherwood Homes Limited failed to ensure suitable contractors were used to carry out the asbestos removal work and demolition of the mill in February 2017. No record of a notification to HSE to remove asbestos had been received for the site. No details of how the asbestos containing materials were removed or how they were disposed were provided to HSE.
Sherwood Homes Limited have had previous enforcement by HSE, including a prosecution in 2018 in relation to their role as a construction client.
Sherwood Homes Limited of Houldsworth Street, Stockport was found guilty to breaching regulation 4(1) of the Construction (Design and Management) Regulations 2015. The company was fined £170,000 and ordered to pay costs of £10,406.
Company director Peter Kiely of Bolton, pleaded guilty to breaching section 37 of the Health and Safety at Work etc. Act 1974, in relation to the company’s failing of regulation 4(1) of the Construction (Design and Management) Regulations 2015. Peter Kiely was fined £6,500 and ordered to pay costs of £7000.
HSE Inspector David Norton said after the hearing, “Asbestos is responsible for thousands of deaths in the UK every year but it only becomes dangerous when it is broken up and fibres are released into the air. Asbestos should only be removed by specialist contractors. Sherwood Homes Ltd and Peter Kiely put workers at risk by not following the correct safety procedures. Companies should be aware that HSE will not hesitate to take appropriate enforcement action against those that fall below the required standards.”
- Aircraft fitter seriously injures hand
- The Health & Safety Event Live: Residents Safety - Lessons from Grenfell Tower
- BSI to offer European certification post Brexit
- £200k fine for poor health and safety management
- Stressful legal matters damaging mental health
- Health & safety regulation to be cut by half
- AIF confirms conference speaker line-up
- BSI to develop stress management standard
- Illegal working crackdown targets rogue employers
- World Health Day 2022
- Real time asbestos detection
- Asbestos: Manage or remove?
- Office expansion
- Asbestos audit scores top marks
- School and glass contractor fined for asbestos failings
- Speedy system
- Ground Gas
- Worker in court after asbestos exposure
- Asbestos: 1.3million at risk?
- Stuart Pearce blows whistle on dangers of asbestos